Definitions
The control room's vocabulary, written once. Detectors, the operator, the map and Ask all read these same definitions, each with an owner, a version history, its SQL and its tests. Where a term has two valid meanings, both are kept and Ask shows both.
Affected customers
Customers off supply right now inside open tickets: every premise whose meter hangs off a transformer an open ticket covers.
Crew sent to a restored area detector
A crew still on the road to a fault whose customers already have supply back: the ticket's meters have sent their restores, so the crew is driving...
Bill about to be estimated detector
A meter that has sent no reads for days with its billing close coming up: unless it is read before the close, the customer gets an estimated bill.
Feeder load
How hard each feeder is working: its peak head load in the period as a share of its rating.
Outage
An interruption the control room is managing: an open ticket in the outage management system, planned or not.
Outage cluster detector
Customers off supply that the control room does not know about yet: meters that sent a last gasp and no restore, grouped by transformer (or by...
Planned work colliding with a fault detector
Booked planned work starting soon on a feeder that has an open fault, or whose tie feeder (its backup supply) has one, or that is itself the...
Priority customer
A premise on the medical priority register: someone there depends on electricity for their health and is called first in an outage.
Priority customer in an outage detector
A premise on the medical priority register that is off supply in an unplanned outage: its own meter sent a last gasp and no restore, or an open...
Restored
An interruption whose customers have supply again, by the ticket being closed in the outage management system.
Reverse flow with no solar registered detector
Energy flowing out to the network from a premise with no generation registered: panels connected without telling the network, or a meter wired...
Sustained outage 2 meanings
An interruption long enough to count against the network's reliability figures. The regulator counts anything over three minutes; network...
Transformer overload detector
A monitored distribution transformer loaded past its nameplate rating for consecutive hours: cumulative heating, not a passing peak.
Voltage out of band detector
A feeder whose end-of-line voltage has been outside the statutory band for several consecutive 15-minute readings, running now.
Meter on the wrong feeder detector
A meter whose supply behaves like another feeder's: it lost and regained power together with a cluster of meters on a different feeder, while its...
Zero consumption at an occupied premise detector
A meter reporting complete reads of exactly zero for days at a premise with an account holder, after normal use before. A stuck register or a...