Feeder Vellmoor Distribution · control room Synthetic data Sun 02:00

Ledger / #161

dispatch crew on transformer 277

T1 done
incident
transformer overload inc_aeb8573be3fb
when
Tue 20:00
call
POST /wfm/work-orders feeder=88 transformer=277 purpose=thermal_inspection
decided by
rules
definition
transformer_overload v1
why
Loading 132% of the rating for 2 hours: send a crew for a thermal check.
controller
Allowed: dispatch_crew is tier 1 (do it and tell); within budget (0 of 12 actions on feeder 88 this hour).
outcome
Crew C-01 sent to CRB6-16/T02 for a thermal inspection, 9.6 km away.
at stake
79 customers on a transformer at 132.0% of its rating

Evidence

customer_minutesNone
customers_at_stake79
feednetwork
feeder_id88
hours_over2
last_hour2026-11-10 19:00:00
peak_kva415.7
peak_pct132.0
priority_at_stakeNone
rating_kva315
stake_note79 customers on a transformer at 132.0% of its rating
started_at2026-11-10T18:00:00
transformerCRB6-16/T02
transformer_id277

Arguments

feeder_id88
purposethermal_inspection
transformer_id277