Ledger / #224
cancel planned work on planned work 134
T2 asked a person- incident
- planned work collision inc_2aa7ce02dd7d
- when
- Thu 17:45
- call
- PUT /planning/planned-outages/134/postpone
- decided by
- rules
- definition
- planned_work_collision v1
- why
- Booked work would take supply off while its tie feeder has a fault: postpone it; a person approves.
- controller
- Needs a person: cancel_planned_work is tier 2 (ask first) in the policy. Postpone booked planned work that would collide with a fault; planning re-books and re-notifies customers.
- outcome
- Needs a person: cancel_planned_work is tier 2 (ask first) in the policy. Postpone booked planned work that would collide with a fault; planning re-books and re-notifies customers. · on-call notified (draft)
- at stake
- booked work on a feeder carrying 155 customers, with no backup supply while the fault lasts
Evidence
| customer_minutes | None |
|---|---|
| customers_at_stake | 155 |
| fault_feeder_ids | [738] |
| fault_outage_ids | [564] |
| feed | network |
| feeder_id | 739 |
| hours_to_start | 4.8 |
| planned_outage_id | 134 |
| priority_at_stake | None |
| reason | pole replacement |
| same_feeder | False |
| stake_note | booked work on a feeder carrying 155 customers, with no backup supply while the fault lasts |
| started_at | 2026-11-12T17:40:08 |
| work_ends_at | 2026-11-13 03:30:00 |
| work_starts_at | 2026-11-12 22:30:00 |
Arguments
| planned_outage_id | 134 |
|---|---|
| reason | open fault on its tie feeder (feeders [738]); work starts in 4.8 h |