Feeder Vellmoor Distribution · control room Synthetic data Sun 02:00

Ledger / #744

cancel planned work on planned work 143

T2 approved
incident
planned work collision inc_95bbe361a6b8
when
Sat 21:06
call
PUT /planning/planned-outages/143/postpone
decided by
rules · Tamsin K. (control engineer on duty, scripted)
definition
planned_work_collision v1
why
Booked work would take supply off while its own feeder has a fault: postpone it; a person approves.
controller
Needs a person: cancel_planned_work is tier 2 (ask first) in the policy. Postpone booked planned work that would collide with a fault; planning re-books and re-notifies customers.
outcome
no backfeed while that fault is open; planning re-books the work [scripted on-call responses (synthetic)]
at stake
booked work on a feeder carrying 171 customers, with no backup supply while the fault lasts

Evidence

customer_minutesNone
customers_at_stake171
fault_feeder_ids[484]
fault_outage_ids[679]
feednetwork
feeder_id484
hours_to_start10.1
planned_outage_id143
priority_at_stakeNone
reasonnew connection works
same_feederTrue
stake_notebooked work on a feeder carrying 171 customers, with no backup supply while the fault lasts
started_at2026-11-14T20:57:05
work_ends_at2026-11-15 12:00:00
work_starts_at2026-11-15 07:00:00

Arguments

planned_outage_id143
reasonopen fault on its own feeder (feeders [484]); work starts in 10.1 h