Ledger / #850
cancel planned work on planned work 150
T2 approved- incident
- planned work collision inc_6b1f44437e5b
- when
- Sat 22:07
- call
- PUT /planning/planned-outages/150/postpone
- decided by
- rules · Tamsin K. (control engineer on duty, scripted)
- definition
- planned_work_collision v1
- why
- Booked work would take supply off while its own feeder has a fault: postpone it; a person approves.
- controller
- Needs a person: cancel_planned_work is tier 2 (ask first) in the policy. Postpone booked planned work that would collide with a fault; planning re-books and re-notifies customers.
- outcome
- no backfeed while that fault is open; planning re-books the work [scripted on-call responses (synthetic)]
- at stake
- booked work on a feeder carrying 49 customers, with no backup supply while the fault lasts
Evidence
| customer_minutes | None |
|---|---|
| customers_at_stake | 49 |
| fault_feeder_ids | [1067] |
| fault_outage_ids | [958] |
| feed | network |
| feeder_id | 1067 |
| hours_to_start | 11.2 |
| planned_outage_id | 150 |
| priority_at_stake | None |
| reason | transformer replacement |
| same_feeder | True |
| stake_note | booked work on a feeder carrying 49 customers, with no backup supply while the fault lasts |
| started_at | 2026-11-14T22:00:30 |
| work_ends_at | 2026-11-15 13:15:00 |
| work_starts_at | 2026-11-15 09:15:00 |
Arguments
| planned_outage_id | 150 |
|---|---|
| reason | open fault on its own feeder (feeders [1067]); work starts in 11.2 h |